Race Against Time To Complete NWTG

BPC Transmission line 2. PIC: MORERI SEJAKGOMO
BPC Transmission line 2. PIC: MORERI SEJAKGOMO

The Botswana Power Corporation (BPC) is in a race against time to reach set targets, but seems to be falling short of meeting the goal to finish the North West Transmission Grid Commission (NWTGC) project on schedule.

The NWTGC project’s progress as at July 2019 was at 73% against the targeted 86%.

However, Project Services manager, George Moeti there has revealed recovery plans in place to catch up on lost time.

Editor's Comment
Stay safe this holiday season

However, amidst the happiness, it is crucial to remember that the holidays can also bring unforeseen challenges. From increased traffic and travel hazards to heightened risks of accidents and social unrest, the festive period demands heightened awareness and responsible behaviour.Traffic congestion and accidents are a common occurrence during the holidays. With increased travel, roads become busier, leading to a higher risk of collisions. Alcohol...

Have a Story? Send Us a tip
arrow up