Francistown Stadium handover date moved to July

Francistown Stadium-1. Pic Keoagile Bonang
Francistown Stadium-1. Pic Keoagile Bonang

FRANCISTOWN: The long awaited 27,000-seater Francistown Stadium will miss the June 8 handover deadline, but the contractor China Jiangsu International is confident the facility would be handed over to the government before the end of July. The project manager, James Tasethabi said the contractor had requested a 35-day extension.

“The main contractor (Jiangsu) is doing remedial works and has asked for an extension from the June 8 deadline by 35 days, meaning that the stadium will be ready by the end of July.  “So far the stadium and overall renovations are almost 90 percent complete. The pitch and works within the ground area is 98 percent ready,” Tasethabi said.

“As for the remedial works, what is remaining is intense finishing of specialisation areas such as electronics and other mechanical fittings. For now, until the handover in July, we will also be carrying out tests on some electronic and mechanical systems we have installed around the stadium.” Permanent secretary in the Ministry of Science Infrastructure and Technology (MIST), Dikagiso Mokotedi said the contractor requested an extension because of delays caused by the Christmas break and other minor remedial works that kept on cropping up during renovations.

Editor's Comment
Botswana at a critical juncture

While the political shift brings hope for change, it also places immense pressure on the new administration to deliver on its election promises in the face of serious economic challenges.On another level, newly appointed Finance Minister Ndaba Gaolathe’s grim assessment of the country’s finances adds urgency to the moment. The budget deficit, expected to be P8.7 billion, is now anticipated to be even higher due to underperforming diamond...

Have a Story? Send Us a tip
arrow up